Background
As part of a facility upgrade, Hastings Deering required a new wash bay water recycling system at its Rockhampton facility.
The wash down water was largely contaminated with dirt and soil, but there was also a small amount of oil and grease entrained in the wash down water that needed to be removed prior to re-use. Bench testing demonstrated that Dissolved Air Flotation (DAF) was the lowest cost solution.
Solution
MAK Water was selected to design, manufacture, install and commission a wash bay water recycling system, working in partnership with Hastings Deering and their Project Engineers.
MAK Water Key Solutions
- A recycling system capable of treating 10,000L per hour of wash down water
- Hydroxide precipitation, flocculation and DAF clarification removes silt, heavy metals, seeds, weeds and pests from the water
- Filters and disinfects the water to ensure it meets safe water and occupational health and safety requirements to reuse for vehicle and equipment wash down
- Supply and onsite installation of interconnecting pipework and electrical
- Fast 10-12 week delivery time
- Onsite commissioning and training of local operators, with ongoing service and maintenance agreement
Results and benefits
- A recycling system capable of treating 10,000L per hour of wash down water
- Hydroxide precipitation, flocculation and DAF clarification removes silt, heavy metals, seeds, weeds and pests from the water
- Filters and disinfects the water to ensure it meets safe water and occupational health and safety requirements to reuse for vehicle and equipment wash down
- Supply and onsite installation of interconnecting pipework and electrical
- Fast 10-12 week delivery time
- Onsite commissioning and training of local operators, with ongoing service and maintenance agreement